Using two languages in p3

Wladyslaw WoloszynMember for 20 years 1 month
Created
5
1
0
Somebody have an idea how to use two languages in p3?
I need to have time schedule english/russian version.
Is it possible and how to do it?
Could be that I can use russian as a log.

5 replies

Oldest first
  1. 0
    Jose Frade ·
    Hi Woloszyn.

    That, is a possbible solution.
    The only thing you need to be aware is that the language you use in a Log field cannot be displayed in columns. It will appear in the gant chart (for instance) next to the activity bar but not as a column like you normaly have for the Activity description.
    I hope it helped some how...

    BR
    JMFrade
  2. 0
    Wladyslaw Woloszyn ·
    Does it means is not possible to have 2 languages description in one line e.g. Activity description:
    Purchase Order / заказ на покупку.
    Or phase description: Engineering / базовое проектирование.
    Only possibility is to haveactivity description in english and log in russian?
  3. 0
    Jose Frade ·
    Good morning,

    The reason to use the two fields is because you are very limited in the number of characters available in Activity description (48). If your act. descriptions are short then you can write boths languages in that field.

    Regards
    JMFrade
  4. 0
    Wladyslaw Woloszyn ·
    Hello Jose,
    Thans for advance. The problem is also with specific russion (cyrillic) fonts.
    Regards,
    W.Woloszyn
  5. 0
    Hannes de Bruyne ·
    Hi Wladyslaw

    I wrote something about using greek and cyrillic fonts in one line in this forum - it is possible but I have to search for it as it is about two or three years ago. Look for the word "greek" if you want to search as well

    Hannes