Critical Path - Graph like S-Curve

Jhorbam Baena OrozcoMember for 17 years 1 month
Created
3
1
0
Hi everyone.

I have to make the graph of the critical path but in a lineal type of graph like s-curve...how i can do that in P3 or excel?...i need a good explanation please...is urgent!!!

Thanks...

3 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Orozco i am not sure about P3 but could do in a spreadsheet by selecting the activities respective durations followed by early dates .Generally this sort of procedure is called line of balance
  2. 0
    Sreejish Vishnu ·
    Hi Orozco,

    I dont know if I understood your requirement correctly. Let me put it this way, - you need to have the critical activities one after the other arranged in terms of the early start/ finish dates.

    This can be done by
    1.Format - organize - Select activity data item - then remove all items under heading ’group by’
    2.Under sort by - selct early start or early finish - order by ascend or descend

    3. go to filter - and select the critical activities with the condition you have for the criticality (total float less than 5 or total float = 0 or whatever)

    This will give you all critical activities listed one after the other.

    I’m not sure whether this is what you are looking for.
  3. 0
    Jhorbam Baena Orozco ·
    Hi Vishnu...sorry but the requeriment was ask to me bad...the people that ask it only need the S-curve but they have a wrong idea.

    thanks