Schedule Percentage complete.

Anbin PonnithMember for 17 years 4 months
Created
3
2
0
Dear All,

Like P6 can we show in P3 the Schedule percentage complete and Performance Complete for all activities..

Also whether the same percentages could be shown in graphical reports?

Please help me..

With Thanks & Regards,

Anbin Ponnith P

3 replies

Oldest first
  1. 0
    Shah. HB ·
    Schedule percentage complete =Planned percentage completion you could do it using tool update progress as of date you need

    Performance completion = actual percentage you plug in activity form and press F9

    you could show both in activity column based on that you could do it in excel
  2. 0
    Osama Warid ·
    I think you do it by using global change
  3. 0
    Anbin Ponnith ·
    Dear Osama,

    Using Global Change we can get Schedule % Complete in the Column Area.But I am not able to get the same in the Graphical report.I am not able to assign a custom data item as a recourse.So it could not be taken for generating graphical reports.



    Is there any solution.

    With Thanks & Regards,

    Anbin Ponnith