Updated prgram as baseline program

Vinod RaturiMember for 20 years 2 months
Created
2
1
0
Hi all ,

Can a updated schedule be stored as a baseline program for further use.

The scenario being that part of out scope has changed after almost 2 yrs , and now the client wants latest updated status to be used as a baseline program .

I tried saving the program as a target program but was unable to do it.

would be helpful , if someone could direct a way out for this.

Thanks

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Vinod,
    Open the project that you wanted to save as target.
    Select Tools->Project Utilities->Copy. Once copied, Select Tools->Project Utilities->Target, select the project copied.

    Note: Only 2 projects can be display at the same time. If already have 2, replace any one of them.
  2. 0
    Shah. HB ·
    Hi vinod

    You can treat the updated schedule as target.Make sure the existing pro-gramme[Which you use for monitoring ] and target should not have same file name.Make sure your target and existing pro-gramme are in one folder