Resources -problems
In the Open Standard
Shareef Abdul AzeezMember for 21 years
- Created
- 8
- 3
0
Hello all
I have been facing situations with resources. I would like your comments ...
The method I adopt once I make the programme is to allocate resources based on production rates, Now I keep the Freeze resources option in P3 unchecked. As such as the programme gets updated (I dont update percentage complete on individual resources as it seems impossible
) as the bugeted quantity is fixed, the unit per time period increases... this is not much of an issue.
the real problem is most of the times I have activities that get suspended for months after it has started or donot get 100% complete ( for example due to obstruciton of area)as such in the programme my activity bar extends far beyond the original duration. In this situation the resources get allocated to all the days and as such when I project the resources using graphs the resource requirements are very high.
I have tried suspend and resume function but I donot believe it helps.
Now the consultants require the resource graphs to be realistic. I have finally only one option that is to get down to each activity and reduce the units per time period and some times bugeted quantity for activties with actual start dates.This way the units per time period donot follow the production rates. I have to adopt this to meet the consultant requirements.
Can any 1 explain how resources are manipulated in P3
I have been facing situations with resources. I would like your comments ...
The method I adopt once I make the programme is to allocate resources based on production rates, Now I keep the Freeze resources option in P3 unchecked. As such as the programme gets updated (I dont update percentage complete on individual resources as it seems impossible
) as the bugeted quantity is fixed, the unit per time period increases... this is not much of an issue.
the real problem is most of the times I have activities that get suspended for months after it has started or donot get 100% complete ( for example due to obstruciton of area)as such in the programme my activity bar extends far beyond the original duration. In this situation the resources get allocated to all the days and as such when I project the resources using graphs the resource requirements are very high.
I have tried suspend and resume function but I donot believe it helps.
Now the consultants require the resource graphs to be realistic. I have finally only one option that is to get down to each activity and reduce the units per time period and some times bugeted quantity for activties with actual start dates.This way the units per time period donot follow the production rates. I have to adopt this to meet the consultant requirements.
Can any 1 explain how resources are manipulated in P3
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?