Resoucre Workage

Ross HatfieldMember for 16 years 5 months
Created
1
1
0
I need to apply a 75% Workload for certian folks. I have tried the Global Change and that is currently not working. Is there a way this can be done.

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Ross,
    Try Global change as shown below and it should work.
    P3 Globa Change

Log in or join to reply