Negative Lag

Mostak MondalMember for 17 years 3 months
Created
5
1
0
Can anybody help me How to filter the negative lag in P3.

5 replies

Oldest first
  1. 0
    Rafael Davila ·
    ST Filter

    In Spider Project you can create both filters, for lag and for out-of-sequence/broken links.

    SP Filter

    If your obsolete software cannot get these essential filters then get more advanced software capable of filtering for lag and out-of-sequence. Missing these filters it is unwise by the developers.

    Negative lag filter would look for lag < 0 but I avoid use of negative lag, only someone auditing my schedule would be interested on using such a filter. If you represent the Owner you should look for negative lag and also for lags too long, say lag > 10 days. The scheduler should explain why use of such values, on very, very rare occasions it might be justified. Misuse of lag can be on purpose, yes dishonest, but a few can dare to do so.
  2. 0
    Ronald Winter ·
    Rafael,

    Perhaps this is off-topic, but why do you keep insisting that SureTrak will positively not work in a 32-bit Windows 7 environment? This simply is not true. I have SureTrack installed and doing quite well on my 32-bit Windows 7 computer.

    Mostak,

    The only way that I know to get a listing of negative lags in P3 of is to export all relationships to either 1-2-3 or dBase and sort on the lag field. P3 and P6 are activity-centric software programs that do not acknowledge relationships except for how they relate to activities. There are no relationship reports, only activity reports with the relationship information included. Good luck!
  3. 0
    Rafael Davila ·
    Ronald

    I appreciate your reply as I would like it to work on my version of windows 7 32 bit professional. I will install it again and see what it shows, and then I will let you know. I hope it works as you said. I admire your insistence on disclosing the truth and not misleading any of our PP friends, if it works I will be honest, not issue at all if I am wrong.

    Best Regards,
    Rafael


  4. 0
    Rafael Davila ·
    ST on Windows 7 pro

    Still not working. I cannot define any resource.

    From:

    http://primavera.zxlm.cn/kb/prim84832

    Problem: Is SureTrak supported on Windows 7?
    Problem: Has SureTrak 3.0c been tested on Windows 7?
    Problem: Does SureTrak run on Windows 7?
    Fix: SureTrak is NOT supported on Windows 7.

    Some of the issues identified with running SureTrak 3.0c on Windows 7 include the following:

    •Cannot create a project using Project Kickstart
    •Cannot create/modify/delete layouts as buttons are missing and the dialog boxes are cutoff
    •Cannot create/modify/delete resources in the dictionary as buttons are missing and the dialog boxes does not display properly
    •Cannot run Tutorial from Help menu

    These issues are not scheduled to be fixed at this time.

    My solution is...

    Remove ST

    Yes ....

    Best Regards,
    Rafael
  5. 0
    Arun R ·

    Hi

    Hi Mondal,

                            Currently you can not add a columns ot show your lag

    However, you can look in the relationship window and scroll thru activity by activity

    The faster way is to export the activites to excel but make sure that you  choose Activity Relationship as the Subject Area.

    Then you will see it in excel