Reprogramming Activities
In the Open Standard
Jhorbam Baena OrozcoMember for 17 years 1 month
- Created
- 6
- 1
0
Hi everybody
I have the follow doubt.
My project in primavera...the original project...have 100 days to complete..in this momment we are in the day number 75 of ejecution...by problems of aprobations from the customer...we have 40 days of delay...and the customer accept the reprogramming of the activities...or in other words the extension of the execution times...they give us 45 days of extensión...
Now, we have to make the reprogramming of this way...example...
Activitie 1.
Days to execution 75
Percent complete 45%
Well to this momment in the control sheet in excel i have to make a "picture" of the information, percents complete of each activitie...and leave all that information freeze...and the leftover percent, redistribute in the 70 days of the work (25 days of the original execution time + 45 days of extension)
I hope that this momment the idea is clear.
Well my question is the follow...How i can do in P3:
1. The extension of the days for each activitie (easy, i figure that i only have to change the finish date)
2. How i can obtain the Resource loading report that adjust to the i explain ...that of leave the first 75 days freeze (like the original data obtain in P3 when the original project was created), but the 70 days of reprogramming take the leftover manhours and adjust to the new duration to obtain or create in excel the S curve with this information?
How can i do that?...Can someone helpme with this information?
THANKS A LOT
I have the follow doubt.
My project in primavera...the original project...have 100 days to complete..in this momment we are in the day number 75 of ejecution...by problems of aprobations from the customer...we have 40 days of delay...and the customer accept the reprogramming of the activities...or in other words the extension of the execution times...they give us 45 days of extensión...
Now, we have to make the reprogramming of this way...example...
Activitie 1.
Days to execution 75
Percent complete 45%
Well to this momment in the control sheet in excel i have to make a "picture" of the information, percents complete of each activitie...and leave all that information freeze...and the leftover percent, redistribute in the 70 days of the work (25 days of the original execution time + 45 days of extension)
I hope that this momment the idea is clear.
Well my question is the follow...How i can do in P3:
1. The extension of the days for each activitie (easy, i figure that i only have to change the finish date)
2. How i can obtain the Resource loading report that adjust to the i explain ...that of leave the first 75 days freeze (like the original data obtain in P3 when the original project was created), but the 70 days of reprogramming take the leftover manhours and adjust to the new duration to obtain or create in excel the S curve with this information?
How can i do that?...Can someone helpme with this information?
THANKS A LOT
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?