Primavera is Not responding

Raed BaderMember for 16 years 1 month
Created
2
1
0
Hi All

suddenly primavera hangs once i open any project either from network resource or from the computer hard drive, it stuck on "opening layout" and at the task manager shows "not responding", but it can open the sample projects which comes with the software.
PS: i am using windows xp.

any suggestions?

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Bader,
    can you create a new project with a few activities, close it and open it again?
    Alexandre
  2. 0
    Ronald Winter ·

    I suggest that you run the

    I suggest that you run the File Fix utility that comes with P3.  Run program C:\P3WIN\P3PROGS\PFXW.EXE, select one of the problem schedules, and check all three corrections to be made.  Good luck!