P3.1 not installing on Windows 7

Sajid SyedMember for 18 years 8 months
Created
7
4
0

i have bought a new computer with Windows 7. i tried to install P3 on windows 7 and that is some how not possible. 

it says

 

"the version of the file is not compatible with the version of the windows you are running"

 

what to do?

7 replies

Oldest first
  1. 0
    Ronald Winter ·

    Loading P3 on a 64-bit Windows 7 computer

    Sajid,

     

    There are two versions of Windows 7; one is 32-bit and the other is 64-bit.  P3 loads and runs fine on a 32-bit Windows 7 machine.  To run P3 on a 64-bit Windows 7 computer is a much more difficult process.  If you use the 32-bit Windows 7, you should not have any problems.  Good luck!

  2. 0
    Mahmoud Amin ·

    P3 Ver.2

    Hi Sayed,

    try installing P3 Ver.2 i think it's ok with win7

  3. 0
    Martyn Davies ·

    If your version of Windows 7

    If your version of Windows 7 is 64 bit then P3 will not run, you will have to set up a virtual machine and instal P3 on that, click on Start\Programs and scroll down to virtual machine and follow the instructions

  4. 0
    Sajid Syed ·

    the 64 bit came already

    the 64 bit came already installed on the machine. when i had this problem, i wanted to install windows XP but they dont have the drivers for it.

    Maybe, ill try through the virtual machine

  5. 0
    Sajid Syed ·

    could not find virtual

    could not find virtual machine in Start / programs.

    can you give a bit more detail

     

    Regards

  6. 0
    Martyn Davies ·

    Start/Programs/Windows

    Start/Programs/Windows PC/Windows Virtual PC