P3 technical glitch
- Created
- 4
- 1
In a 3 month programme I prepared, I added additional detailed activities and after I F9’d I left it open on my PC while doing other task.
When I returned to have a look some activities gradually disappeared from the screen. I’m not sure what I clicked but to verify what was going on I activated the filter and one by one the remaining activities also disappeared. I checked ‘all activities’ filter and it returned a blank screen save for the time scale.
Petrified, I went to the project overview and it shows total number of activities which means it does not banish at all. This time I ran schedule again and the report is not encouraging….it says predecessors and successors cannot be found!
I noticed something though in the overview – the data date is 18 October 2010 but the early finish is 08 Dec 08! I believe this is what causes it but I just don’t know how to fix it.
This is the first time that I have encountered this problem.
Anyways, does anyone here come across with this type of glitch before? And if you do, can you please share how you fixed it? Thanks in advance.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?