Hi,

What method to follow to save the data in the schedule(for eg: cost, budgeted quantities etc) while next updating of the schedule.

Thanks in advance.

Kannan

2 replies

Oldest first
  1. 0
    Ronald Winter ·

    Kannan,   You should never

    Kannan,

     

    You should never modify your schedule once you published it.  Instead, you should make a complete copy of the schedule (under Tools / Project Utilities / Copy) and then update the copy.  Leave the old schedule untouched so that you can use it as a baseline.  Good luck!