problems on update data date
In the Open Standard
Ji WeiMember for 16 years 5 months
- Created
- 3
- 2
0
Hi:
When I update the data date in my P3 schedule, My steps as follows:
1. update all activities weekly
2. update data date weekly
3. schedule
Problems:
The early finish dates (already actual started activities) also prolong one week after I updated the data date. And the early finish dates is later than data date. I think these acutal status activities should not move when I update the data date. So that I need come back, and carefully check the started activities. And update the changed activities.
Any one knows what problems I have made?
Thanks for your help!
3 replies