Primavera Contractor S Curves

Tony SewellMember for 16 years 1 month
Created
1
1
0

Hi,

I want to be able to show a simple S curve based on a baseline and the remaining works. I only want this to be based on the duration of the works rather than resource.

 

Meaning that I can easily produce an S curve showing the profile of the works without having to resource the entire programme.

 

I am aware of the Resource Curve Tab, but these curves are not explained and can not be edited to include baseline etc.

 

All i can think at the moment is to create a new Report to export to excel to create my own, unless anyone is aware of another option?

 

Thanks

 

Tony

1 reply

Oldest first
  1. 0
    Mohammad Mojahid Akhtar ·

    Dear You can get the S -

    Dear

    You can get the S - Curve for duration. Do one thing put One Resourse (  say  - Parameter ) to all activity with 1/d .

    then go to Report option and extract report from resourse & roll assignment.

    you will get S -Curve.

Log in or join to reply