Primavera Contractor S Curves
In the Open Standard
Tony SewellMember for 16 years 1 month
- Created
- 1
- 1
0
Hi,
I want to be able to show a simple S curve based on a baseline and the remaining works. I only want this to be based on the duration of the works rather than resource.
Meaning that I can easily produce an S curve showing the profile of the works without having to resource the entire programme.
I am aware of the Resource Curve Tab, but these curves are not explained and can not be edited to include baseline etc.
All i can think at the moment is to create a new Report to export to excel to create my own, unless anyone is aware of another option?
Thanks
Tony