PROGLOC directory is invalid. Please Check your P3.INI file.

Ruel CatapangMember for 14 years 7 months
Created
1
2
0
Ive just had my hard drive re-formatted on my company laptop and had to reload P3. I keep getting the same message...................PROGLOC directory is invalid. Please check your P3.INI file.
Ive tried to mess about with the P3.ini file but it still doesnt work
Can anyone help

Thanks

1 reply

Oldest first
  1. 0
    Jose Frade ·

    Be sure to have installed P3

    Be sure to have installed P3 on the root directory....

     

    P3 does not support to much long path ( Needs to be less than 64 chars.)

     

    BR

     

    JMfrade