Which smart features of P3 do you miss?

Erdem UysalMember for 18 years 3 months
Created
6
4
0

I have been using P6 since 2008 but I still miss some smart features of P3.  My favorite two is below. What is yours?

- Floating successor, predessor and recources windows.

- Smart keyboard shortcut keys which lets you navigate, input and check the data through the programme quickly.

6 replies

Oldest first
  1. 0
    Joe Robertson ·

    For me it has to be target

    For me it has to be target comparisons. I'm not a fan of how P6 "swallows" what I declare to be the baseline. It's hard for me to picture Primavera debating this feature and deeming it an improvement over P3's method.

    But I will agree with you about the floating windows. I have dual monitors and it hurts my productivity to cram so much on 1 screen.

  2. 0
    Mike Testro ·

    Hi ErdemIts not smart as such

    Hi Erdem

    Its not smart as such but the ability to put a different colour on each task was an essential element dropped by P6.

    Best regards

    Mike Testro

  3. 0
    Vladimir Liberzon ·

    It does not look like people

    It does not look like people miss something serious.

  4. 0
    Mimoune Djouallah ·

    the resource usage profile

    the resource usage profile was much better in P3, a lot of different combinations in resource histogram were possible. the option of hammock  between two activities was lost in the transition.

  5. 0
    Vladimir Liberzon ·

    Hi Mimoune,what is the option

    Hi Mimoune,

    what is the option of hammock  between two activities that was lost in the transition?

    Regards,

    Vladimir

  6. 0
    William Chee ·

    in P6 the feature LOE

    in P6 the feature LOE (activity type) is same with hammock.  I missed "zero total float" and floating windows in P3.  Key in data is a lot faster in P3 compare to P6.