Suretrak 3.0c automatically reorganizes activities on startup?

Monty RobisonMember for 12 years 9 months
Created
6
4
0

Hello,

Hopefully this is the correct forum for this post. I'm having a problem I hope someone can help with. I'm using Suretrak 3.0c. When I go to Format>Organize and uncheck the Reorganize Automatically box I'm able to insert new activities and move them where I want them just fine. The problem is when I close the file and then open it back up Suretrak reorganizes all of the activities even though the box is still unchecked. Is there a way to prevent this behavior and have Suretrak not reorganize all of the acitvities when opening a file? It's very frustrating to move a bunch of activities where you want them only to have Suretrak negate all of your efforts. Thanks in advance for any help you can give me with this.

sparky55

6 replies

Oldest first
  1. 0
    Rafael Davila ·

    Suggest making a simple

    Suggest making a simple activity order change, then perform a save just before closing, it might be changes in activity ordering are not interpreted as a file change unless you specifically state it by executing a save action.

  2. 0
    Monty Robison ·

    Rafael,Thanks for replying. I

    Rafael,

    Thanks for replying. I tried exactly what you suggested and to no avail. After moving an acivity I saved the project and exited. When I re-opened the project the  activities reorganized themselves numerically even though the box is unchecked under Format>Oraganize to "Organize Automatically". Any other suggestions?

    Monty

  3. 0
    Rafael Davila ·

    Try going to Organize and

    Try going to Organize and look for any sorting selection, if there are sorting order specified un-clik/delete them and see what happens after you have manually changed activity sorting.

    It might be just the opposite that when you do not have a sorting criteria then Suretrak will use activity ID. Therefore I would try selecting any sort criteria but with Reorganize automatically un-clicked as to prevent default sorting from happening.

    • If you do not specify sorting criteria, or if all other sorting criteria are the same for two or more activities, SureTrak sorts by Activity ID

    The last option that occurs to me is using a comment field or user defined field to create sort order numbers and place sequentially the values. This have the advantage of when changing/resorting layouts you can recover the sorting. 

    • If you define a custom sorting field for each layout then you can define sor order numbers by individual groups without need to change all fields. 

    Good luck, this is as far as I can go without the software.

    Best Regards,

    Rafael

  4. 0
    Johannes Vandenberg ·

    Hi MontiI have not

    Hi Monti

    I have not expierieced this with Surtrak. Here you find a link how i have organised my schedules in Suretrak.

      https://www.mediafire.com/?0a2pvn6avobl34o

     

     

    Regards Johannes

     

  5. 0
    Rafael Davila ·

    Charlie,I have not used

    Charlie,

    I have not used Suretrak for years but suggest unlink % complete and remaining duration and also consider changing % complete to 0 though not sure.

    Good luck.

  6. 0
    Johannes Vandenberg ·

    Hi CharlieYou could sent me a

    Hi Charlie

    You could sent me a copy of you schedule. I have Suretrak still running on my vitual machine.

    See what i can do.

    Regards Johannes

Log in or join to reply