Payments schedule

Marcio SampaioMember for 21 years
Created
4
22
0
Dear all,

I’m thinking about create a payment schedule on P3e. My initial idea is to create a schedule with milestones - payment events - and define expenses for this milestones. So i can create a histogram and s-curve on P3e.

Is it going to work??

I’d like to know your opinion.

Best regards.

Marcio Eduardo

4 replies

Oldest first
  1. 0
    Muhammad Iqbal ·
    yes it is very nice idea from u
    but you will be happy to hear that i have already worked on it.

    in Saudia i was been practising

    Details can be provided

    have fun

    iqbal
  2. 0
    Marcio Sampaio ·
    Thanks Muhammad,

    I already did the Payments schedule and it is working. The most difficult thing is to do the links between the activities that generates payments events and the milestones.

    I create a diferent project with the milestones - payment events - and integrate with the timeschedule. For the time being, it’s working.

    Any opinion??

    Regards.

    Marcio Eduardo.
    Rio de Janeiro - Brazil
  3. 0
    Muhammad Iqbal ·
    HI
    Marcio Sampaio


    I was doing it by % wt Assinment .

    so at the end of month wat so ever will be EV same will paided to contactor so very sipmle

    can i have your project so that i can reveiw and comments

    regards
  4. 0
    Marcio Sampaio ·
    Hi Muhammad,

    The project file is too big (more than 7.000 activities - 20 MB).

    Regards.

    Marcio.

Log in or join to reply