Del acitivity code assignments

Mohsen NourbakhshMember for 19 years 8 months
Created
3
25
0
hi guys,
we’ve just started to run P3e parallel to the P3, so I’m fairly new to P3e. was trying to delete activity code assignments(code value) of some activities and simply make the field blank but it wont delete (EPS,Project, Global level) , just allows me to change it to another one(dont know if it s an access right issue, yet can add/del/edit activities and Project level codes, ...). any ideas? cheers

3 replies

Oldest first
  1. 0
    Andrew Dick ·
    You should be able to open the ’Activity Details’ at the bottom of the layout, go to the ’Codes’ tab, select the code you wish to remove and click on the remove button at the bottom.

    Andy
  2. 0
    Niek Zonneveld ·
    Just bring the activity code column into the layout and use copy-down (ctrl-E). If you copy down from an empty field you effectively delete the codes.

    HTH
  3. 0
    Mohsen Nourbakhsh ·
    Guys Thanks so much, Now that the problem s been solved i feel like i m the dumbest ;)