Skip to content

Migrating From P3e V 4.1 to V 5.0 (Baseline )

William DesameroMember for 20 years 9 months
Created
5
25
0
Hello Everyone,

We recently upgraded our P3e from version 4.1 to 5.0. Importing of projects were successful but the project baselines were not captured. Can we import projects including its baselines?

Regards,

William

5 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    I’m afraid you can’t William.

    You should unlink the baseline in the 4.1 schedule and import these separately.

    H.T.H.
  2. 0
    William Desamero ·
    Thanks Niek!
  3. 0
    Patricia Le Clainche ·
    William,

    I am just a user, and do not know all "secrets" of migration. But I am a little bit surprised of this problem. I am quite sure there is a way, that doesn’t need to unlink baselines. I nether heard of this problem (and projects I am working for had also migrated from V4 to V5 with their baselines). I hope someone else has the answer.

    Best regards.
    Patricia
  4. 0
    Dieter Wambach ·
    Salut Patricia

    There are two ways:
    1. The normal way to start a SQL-Skript on the CD to transform the database from 4.1 to 5. Later the user will just realize some different screens and functions. Most IT departments inform the users. Baselines are still connected.
    2. Single projects to be transferred e.g. from a backup database. Then it will be the complicate way as described by Niek - unlink --> export projects + BL --> import --> link again.

    Regards and a have a nice Sunday

    Dieter
  5. 0
    Patricia Le Clainche ·

    Hallo Dieter,

    Thanks for this info.

    Bis bald !
    Patricia

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?