Targets date being pulled forward

Mangesh KhuspeMember for 19 years 7 months
Created
1
16
0
hi
all i have problem with p5
i sechedules and after that the targets date changed and they became whatever the date that were after scheduling and changing data dates.

regards

mangesh

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Mangesh

    Did you asign a baseline? Projects --> Assign Baseline.

    Regards
    Dieter