Skip to content

Floats and Auto Level,,Please Urgent reply

Minhas ShaikhMember for 19 years 7 months
Created
8
30
0
Hi,
Anybody knows about resource leveling?
I have a schedule in I have assigned resources as a non labour . I have assigned quantities . Budget and actuals as well. I have to level those resources thereofore after leveling schedule changes all finsh and start dates but it doesn’t changes total and free floats.
I haven’t done resource levelling before.
Am I assigning wrong ’ativity type’, or ’resource units’ or ’constrants’ or ’float calculation’?
Can anybody solve my problem. Quick reply would be highly appreciated.

8 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Minhas,

    You have to select the resource to level first and add leveling priorities of which activities should level first when conflict accours. Make sure that you also set the maximum quantities of resource available as a boundary for your resource leveling.

    Hope this help,
    Rodel
  2. 0
    Minhas Shaikh ·
    Dear Rodel,
    Thanks for reply.
    I have leveled and prioritised everything is calculates but only float is not calculating properly. Only it works on half of the schedule.
    Please reply...
    Minhas
  3. 0
    Rodel Marasigan ·
    Minhas,

    Check your maximum allocation. It may not enough to cover your resource requirement. This will still show delay on other activities. Also check other resources if has been leveled for those activities that not affected. You can do this separately or per resource and check the difference.

    Hope this help,
    Rodel
  4. 0
    Minhas Shaikh ·
    Thank you Rodel.
    I have assigned about 5000 per week from Jan to December 2007, after that 7000 per week . That’s working and graphs is almost fine and dates are also fine. But I am not getting float . Folat valus are same as before leveling .
    If dates are changing then float should be changed.

    Thannks

    Minhas
  5. 0
    Rodel Marasigan ·
    Minhas,

    Check your critical path and critical activities. Try to compute manually using forward pass (LS-ES) or backward pass (LF-EF) if you will have same result. You might have same float because critical path still the same.

    Hope this help,
    Rodel
  6. 0
    Vladimir Liberzon ·
    Minhas,
    Primavera does not level non labor resources.
    Regards,
    Vladimir
  7. 0
    Naveen Paladugu ·

    _ve float explains delay of

    _ve float explains delay of project i.e -6d float means project is 6 days behind schedule..You can get -ve float values in P6. Go to columns---->Durations----->Total float

  8. 0
    Shahajahan Azeez ·

    Dear All,Any body help me

     

    Dear All,

    Any body help me regarding the -ve Float

     

    After Updating the Program in P6,we have number of -ve floats, how to check the certain value of -ve Float    (For example  -33d Float) ???  

    How to filter the -33d float in P6

    Regards

    Shahajahan

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?