P6 Interproject Relationship Imports

Oli KallenbornMember for 18 years 11 months
Created
2
15
0
Hey all,

I am currently tracking milestones in a single project, and these are all linked to other projects.

Some of the links are broken by the planners during updates.

Is there anyway of importing interproject relationships, because I have not been able to successfully do so.

Thanks

2 replies

Oldest first
  1. 0
    Waseem Saber ·
    When you import you should untick the relationship between only copied activities, this should be able to bring all the relationships with other projects.

    hope this helps.....

    Waseem Saber
  2. 0
    Oli Kallenborn ·
    That won’t help you maintain existing links in your existing project that you want to update.

    That will merely keep the links in your new update.

Log in or join to reply