p5 __ text not showing in print

Kier LegardMember for 20 years 3 months
Created
5
14
0
Hi to all,


Im printing a schedule but text in the schedule is not showing.This is my first time to encounter this. I did not change the setting in the printer.My previous print is ok.

Please help.



Regards,

kier

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Kier
    If the table isn’t printed: File --> Print preview --> page setup (the icon in the upper left corner) --> option --> mark "activity table" --> "Apply"
    If I understood your question correctly, then this should work.
    Regards
    Dieter
  2. 0
    Kier Legard ·
    Hi Dieter,

    Actually it is marked so it should be showing in the print .In fact the activity table is showing without the text.



    Regards,

    kier
  3. 0
    Dieter Wambach ·
    Is it shown correctly in the preview?
  4. 0
    Kier Legard ·
    Hi Diter,


    Is is showing correctly in the preview.



    Regards,


    kier
  5. 0
    Dieter Wambach ·
    Kier
    The reason probably is the printer or the driver.
    Is the correct driver installed?
    If you have access switch off the printer, wait a minute, then switch on again.
    If still not ok, try a different font - arial in general works.
    Can you print-out docs with the same font out of your word-processing system?

    The reason is not P6.
    Good luck!
    Dieter