Calc Costs from Units feature v6.1
In the Open Standard
John HartmanMember for 21 years 2 months
- Created
- 1
- 9
0
Can anyone let me know if this feature can be applied to remaining units only? It appears it’s used in conjunction with the auto compute actuals tag.
What I’m trying to do is import actual hours/cost and have the remaining cost calculated by the remaining units (hours). But it seems to overwrite the total cost (incl actual cost) when I modify the remaining units.
What I’m trying to do is import actual hours/cost and have the remaining cost calculated by the remaining units (hours). But it seems to overwrite the total cost (incl actual cost) when I modify the remaining units.
1 reply