Finanical approval calendars

Nathan BurmanMember for 18 years 11 months
Created
2
24
0
I need to create a calendar for financial approval meetings and would like to start from a calendar with zero working days to allow specific work days representing dates the financial approval can take place.

I can do it the long way but wondered if anyone knew a way to force P6 to create a calenar with a standard work week of zero days?

I’ve tried and when you click ok on the work week with all the days set to 0 hours it return to the default hours.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Nathan

    As far as I know the lowest value is 1 day with 1 hour. Currently I have no idea for a good workaround.

    Regards
    Dieter
  2. 0
    Nathan Burman ·
    Thanks Dieter,

    I didn’t think it was possible besides having a 1 day week and setting most days to non work.

    I’ve actually done this the long way now but if anyone else has a faster way to do it I’d be interested to know.

    Regards,

    Nathan