P6 Report Loading Error

Izam ZakariaMember for 20 years 5 months
Created
4
19
0
Guys,

I’ve a problem currently which BQ was uploaded for quite example 10 000 mhrs. But the report just shown 1 000 mhrs (period totals)column only.Another 9 000 mhrs was allocated on (post) column.What the heck is this? I did on others project which used the same report group resource and the result is perfect. Guys pls help me

4 replies

Oldest first
  1. 0
    Izam Zakaria ·
    To make it clear, it’s loading 5 mhrs only per week....
  2. 0
    Arnold Puy ·
    Hi Izam,

    Can you cite an example, a little bit clearer.

    Regards,

    Arnold
  3. 0
    Izam Zakaria ·
    Hi Arnold,

    Sorry for not making it clear since I’m too rushing yesterday

    As we know Budgeted Quantity = Original duration*units per day right? but the problem is all my UPT (units per day) remain to 1. Is not suppose to be, becuase it would calculate automatically once we drop BQ and OD status.

    What I did yesterday, I convert it to P3 version then export it to excel direct do correction.

    Done perfectly, but I didn’t find it at P6 software. Could u tell how to do this at p6 via excel spreadsheet?
  4. 0
    Arnold Puy ·
    Hi Izam,

    Okey. You mean Export P6 to Excel sheet. You can even do this in P6 itself using global.

    So, what exactly you need to export and modify it in Excel? The Units/Time, Budgeted Units or Duration?

    I think the reason why the UPT remain to 1 it is because, the duration type is "Fixed Units/Time". Try to change it to "Fixed Duration & Units".

    Now if you are trying to update your schedule, the UPT will change depending on the "Remaining Duration & Units".

    Hope this helps.

    Regards,

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?