Dear All,



My project id is TEL1. Whenever I am going to create WBS , it expands in such away TEL1.1 , TEL1.2 . But I do not want this type of WBS and Wants like T1.A , T1.b. Is it possible in primavera to define characters for WBS ?


Regards,

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Rohit,

    Unfortunately No. Because the WBS always start with the Project ID and followed by the WBS Code.

    The only way is to change your Project ID into T1 and input manually the WBS Code A,B.....C.

    Regards,

    Arnold
  2. 0
    Rohit Rangnekar ·
    Thanx sir