Level Resources automatically getting ticked

Haresh JayanthMember for 20 years 2 months
Created
1
13
0
Hi Rodel,

Before importing a program , i untick the option in Tool , Level resources , "Level all resources".

But when i import a program back , this option "Level all resources" is getting activated again"......

Even when i am importing i have removed "Keep existing option for all the parameters to "Update existing" still i am not able to remove this option..

Kindly advice....

regards,

Haresh Jayanth

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    Scheduling Options and level options settings are exported in XER under SCHEDOPTION table and it will keep the settings option if your import action is to update the existing database or Project. If your import action is Create New Project then all settings will goes back to default like level all resources and preserve scheduled early and late dates etc…

Log in or join to reply