STEP-BY-STEP GUIDE USING SDK IN SCHEDULE PREPARATION
In the Open Standard
JR
Jeoffrey ReyesMember for 18 years 4 months
- Created
- 281
- 1,002
0
Hi guys,
I wrote a short paper about the steps on how to use Software Development Kit (SDK) in Schedule Preparation. It is very simple, full of screenshots and easy to understand especially made for those who are beginners in SDK. I hope it would help some of our PP members who just came in and for those who are newbie in SDK.
I would like to share it to all our PP members who are interested. Just post your e-mail and i will send it to all of you.
Cheers,
JEFF
281 replies
Oldest first- 0JRJeoffrey Reyes ·Hi Roozbeh,
As i have mentioned in my SDK GUIDE you will be needing;
1. Activity
2. Dictionary
3. WBS
What i used there is a compatible version for 6.x. I am using also version P6.v7. Many had requested under my thread and if you want it I can share it with you.
Cheers,
JEFF - 0PLPaulino Lacaste ·Hi Jeff,
I have a problem, After filling the WBS names and click the update project list button, the excel hang. I am using a P6 server, also my computer setting does not have Primavera SDK. The system DSN is Visual Fxo Pro database.
Could you please advise?
Thanks in advance.
Paul - 0JRJeoffrey Reyes ·Hi Paul,
You have to set first your SDK to ODBC. Go to your control panel=>Administrative Tools=>Data Sources(ODBC)....Click ODBC then click the TAb System DSN=>Add...then look for Software Development Kit...click it then Finish.
Your SDK will be shown then Configure it....put ODBC Name Primavera SDK..then OK.
When logging in to your P6...choose PMSDK as your database...then put your PC Name/PRIMAVERA as your Host Name and pmdb$primavera as your database name...Let me know.
Cheers,