Skip to content

Remove performace % by Global change

James bidMember for 17 years 1 month
Created
3
14
0

Dear experts!

 

May I ask your help on what parameter to use in removing the performance % in each activity.

I tried the

If

Activity status is not equal to Not started

Then

Physical % = 0

 

But the % didnot change.

 

Hoping to share your knowledge on this matter.

 

Many Thanks

Chris

3 replies

Oldest first
  1. 0
    Roger Booth ·

    How to deprogress a project

    1. Choose 'Enterprise', 'Projects' and select the calculations tab. Choose 'Link budget and at completion for not started activities' and 'Reset remaining duration and units to original'

    2. Choose view,columns and add the columns for 'Actual labor units' and 'Actual non labor units'

    3. Choose tools, schedule and set the data date equal to the project start date and schedule. To find the project start date, choose Enterprise, Projects. click on the dates tab and note the planned start date.

    4. For the first activity in the list, set the actual labor units to zero. Highlight the activities in this column and choose edit, fill down

    5. Do the same for the actual non labor units

    6. Global changes then required

    Subject area - Activity Resource Assignments

    Where Resource Type = Material

    Then Actual Material units = 0

     

    Subject area - Activities

    Where activity status is not equal to not started

    Then activity status = Not started

     

    Subject area - Activities

    Where activity status = Not started

    Then Remaining duration = Original duration

     

    Everything in the project is now not started and reset to original programme

    Regards

    Roger

  2. 0
    James bid ·

    Thank you Roger for the

    Thank you Roger for the detailed information you had given to me.  My programme was reset already.

  3. 0
    Evans Musyoka Matinge ·

    Global Change for Deprogressing

    Simply deprogress by,

     

    If

    Physical % Complete is within range of 1% and 100%

     

    Then

     

    Physical % Complete = 0%

    Duration % Complete = 0%

    Actual Start =            

    Actual Finish =

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?