Price/Unit for resources in Primavera P6

Mark DunnMember for 16 years 2 months
Created
5
48
0

I have one plan and two P6 users accessing it.  The price/unit for resources changes when either of us are in it.  There must be a check box somewhere to stop this happening, probably in user preferaces.  When one of us use it the price per unit is £39, when the other uses it it is £26.72.  Can anyone help?

5 replies

Oldest first
  1. 0
    David Kelly ·

    It is the project, not the

    It is the project, not the user that has the default price...

    What do the two users see when allocating a resource assignment if you add the fields "Rate Type" and "Rate Source" to the resource assignments tab in activity details?

  2. 0
    Mark Dunn ·

    Thanks Dave.  Sorry for not

    Thanks Dave.  Sorry for not getting back sooner, been away.  I understand the project has the default price, but when we are in it we see differnt prices depending on the user.  We both see 'Price/Unit' and 'resource' in the rate type and rate source fields.  When my colleage is in the project a resource rate is £68, when I am in it it is £46.59.

    Mark

  3. 0
    Karl-Heinz Knoche ·

    Hi Mark,recently I had a

    Hi Mark,

    recently I had a similar problem. Check "Edit" -> "User Preferences" -> "Currency" and make sure you both use the same one. On my system someone installed two times Euro (Euro and EUR).

    Hope this helps!

    Karl

  4. 0
    Mark Dunn ·

    Karl, That's it.  I new it

    Karl,

    That's it.  I new it would be something simple!

    Thanks, Mark

  5. 0
    Umair Arshad ·

    My understanding is that

    My understanding is that price/unit is aloted to resources in the database, not the project. Each time you alot a different price/unit to resource and recalculate the project, it will automaticaly change the price/unit of resource aloted to each project. So be careful by changing the price/unit of any resource.

    It is possible that both of you have selected different resources. Try to delete that resource and again add it with same price/unit.