How to feed directly the quantities of a Resources in the spreadsheet of Primavera P-6
- Created
- 15
- 58
Dear Friends,
I need S-Curves of a Resource (like Concrete) in terms of (a) Quantities and (b) Cost in Primavera P-6. To do this I follow the following Steps
Step 1: I go to Enterprise > Resources > add a new Resource > here in new resource wizard assign resource ID, Resource Name, and then Finish. Now In Resource detail tab tick on material, drop down unit of measure and I assign meter cube for Concrete. Now in Unit & Prices tab I assign Max Units/ time (for Concrete I assign 1000 meter cube per day) and I also price/ unit from the BOQ price.
Step 2: Now if I need to assign this resource (concrete) then I select the activity and in activity detail tab > Resources > add resource and here I put Budgeted Units from the BOQ.
Step 3: and then to Resources usage Profile.
Now my Problem is this I have too many activities, and hence it is too much time consuming to select each activity individually and then to go to step 2. So is there any way like to feed directly the quantities in the spreadsheet of Primavera. The Quantity Surveyor gives me the quantities of activities in tabular format and if I can directly put in spreadsheet without selecting each activity and to follow Step 2, then I can save my considerable time.
I will appreciate your help and Time.
Best Regards
Faisal Hashmi
15 replies
Oldest firstLog in or join to reply