Baseline dates are different after it incorporated to another schedule

Krishna KumarMember for 19 years 9 months
Created
5
35
0

Hi Planners,

                I am facing some problems in assigning Baseline to my current schedule. After completing the monthly progress updation on my current schedule, i copied it as a another project to use it as another baseline. But once i assigned this as new baseline schedule and assigned it as Project Baseline. But the dates are not same as the original.

If i view the baseline schedule alone, its showing different dates & if i incorporate it into another schedule it showing different dates. I don't know why it showing like this. Kindly help me to resolve this ASAP coz i've to submit the Schedule within 2 days.

 

Regards,

Krishna

5 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, First, Check the Calendar

    Hi,

    First, Check the Calendar if the default is the same as the Project activity calendars.

    Second, I doubt maybe you are looking on the columns showing the Planned dates. Planned dates is different from the baseline dates.

    To make sure of it, use the Gant bar to compare Current Schedule from Baseline Schedule.

    Hope this will help.

     

    regards,

     

    Raymund

  2. 0
    Krishna Kumar ·

    Hi

    Hi Raymund,

                       I have assigned it as Project Baseline & looking in Project Baseline start & finish. And one more thing that while preparing the baseline i have entered some actual dates but now after assigning it as baseline the dates are not same as the actual date that i have entered.

    And i don't know that if anything wrong in the method of assigning the baseline, could you clarify me that after updating all the actuals if i want to save it as a baseline what is the exact procedure? Kindly clear me ASAP coz i have to submit in 2 days.

     

    Regards,

    Krishna

  3. 0
    Kumar Baiju ·

    Dear Krishna           If you

    Dear Krishna

              If you give some screen shot then it helps me to understand in better way.

     

    Regards\\

  4. 0
    Gary Whitehead ·

    Open the baseline schedule,

    Open the baseline schedule, and run a global change to make planned dates = early/actual dates.

     

    This should fix the problem.

  5. 0
    Krishna Kumar ·

    Hi Friends,

    Hi Friends,

                    Thanks for your support to solve this issue. And i've got my dates by following Arnold suggestion as below,

     
    User offline. Last seen 1 week 3 days ago. Offline
    Joined: 2007-04-25
    Content Credits: 1106
     
    Add Contact-Network
    Hi Rav,

    Why do you want to update your Baseline?

    Anyway, to update your Baseline, go to Project Menu --> Maintain Baseline --> Highlight the baseline & Select Update, Mark the “Update existing activities already in the baseline” & select Update Options, Mark the necessary checkboxes you need especially “Dates, duration and data date” then OK and UPDATE.

    Notes: If you choose the ’Dates, durations, and data date’ option to ensure that these fields are updated, after you run the baseline update, you should restore the baseline project, then schedule and re-baseline the project.

    HTH.

    Arnold
     
    So, finally it works & got the dates that i've required.
     
    Regards,
    Krishna
     
     