Budgeted Quantities being divided by hrs when importing
In the Open Standard
David MurphyMember for 18 years 1 month
- Created
- 1
- 20
0
Hi Everyone
When I import a XER file sent to me and open it up, the budgeted quantities in the resources has changed – after some investigation I realised each time I import it is dividing the budgeted quantities by 8 – I presume this is because there are 8 hours in the day in the calendar.
Can anyone please advise how this can be avoided?
Thanks