Updating resources dictionary by importing from Excel

Hussam EldinMember for 13 years 8 months
Created
1
16
0

Dear Planners:

When I tried to import an Excel file to update the rsources dictionary , the only  data that successfully updated was the Default Unit/time column ,the other Data like adding new resources, price/unit ,unit of measure and even the new recources which I added through Excel had not been updated or imported.

Any ideas about how resources dictionary could be updated through Excel file ??

Regards

1 reply

Oldest first
  1. 0
    Hussam Eldin ·

    Just to assert I am using P6

    Just to assert I am using P6 V7.00