Skip to content

Define Total Project Percentage on EPC Projects

Tony SheltonMember for 23 years 9 months
Created
19
4
0
How is the total project percentage calculated on Engr-Procuremnt-construction (EPC) projects? Is basis on financial solely or some other method? Would like to see how others are doing it.

19 replies

Oldest first
  1. 0
    Tomas Rivera ·
    Tony:

    What do you mean by total project percentage?

    Tomas Rivera
  2. 0
    Tony Shelton ·
    The total combination of engr. complete, procurement complete, and construction complete. Financial completion is easily calculated. I am looking for what other EPC contractors are utilizing if at all. Do they have owners and PMs asking for this information? Beyond the financial answer, I not sure how you might show or calculate the value, or if it would trully be meaningful.
  3. 0
    Tomas Rivera ·
    Tony:

    I think you are refering to the weighting method or weight factor for assessing the value of activities for progress evaluation.
    There is a good discussion about this subject in the Planning, Scheduling and Programming Discussion forum under the title "Weight Factor". It might answer your question.

    Tomas Rivera
  4. 0
    Hal Macomber ·
    Tony,

    I work with a number of EPC contractors. There is a shift underway away from using these weighted performance measures. Even Microsoft has noted the limited value of percent complete data. See: Microsoft Eats the Dog Food. The conclusion contactors are reaching is we must measure the completion of work according to plan rather than the progress of work usually in hours applied versus planned. The first is a measure of reliability. The second is often construed as a predictor of performance.

    The measure for plan reliability percent of plan complete (PPC) is easy to use. Calculate the percent of tasks completed as planned in a time period. For instance, 2 tasks planned for completion each day during the week. Lets say the two tasks were missed on Monday, but all other tasks were completed on the days planned. The performance would be 80%. Performance can be calculated by major performer (specialty contractor) and aggregated without dealing with averages of averages.

    The principal reason firms are moving to this measure is task starts (and finshes) on projects usually depend on the completion of other tasks. The PPC measure addresses the fundamental variable in improving the flow of work on the project.

    Hope this helps.
  5. 0
    Forum Guest ·

    Define Total Project Percentage on EPC

    I have written an paper on the practical applications of Earned Value Performance Measurement which outlines some of the issues discussed here, you will find it under the heading "Technical Papers".

    There are a number of percentage completes that may be calculated and they all provide a different view of the project.

    Typically I discuss:
    1. % of Hours
    2. % of Costs
    3. % of Deliverables produced in terms of Cost or Quantity.
    4. % of Time expended

    These percentages may be presented as
    1. % Original Budget
    2. % of Current Budget
    3. % Forecast Cost at Completion.

    The ones that are monitored very much depend on the drivers of the project:
    1. Is the project time, cost, resource or risk sensitive?
    2. Are you the client or the contractor or is it an inhouse project.

    Regards

    Paul E Harris
    Eastwood Harris Pty Ltd
  6. 0
    Forum Guest ·

    [duplicate post]

    [dulplicate post]
  7. 0
    Mehdi Rashidi Alangeh ·
    Dear my friends,
    You must calculate weight of this items ( E & P & C) with cost norm and then calculate Progress report.

    Regards
  8. 0
    Morteza Jafari ·
    dear, I advise to useing manhours base if you have it give the best weight factor in project, cost base may give the wrong progress dring exceution project, because you are seeing everything from view of cost not physical.
  9. 0
    Forum Guest ·
    Dear morteza,
    You are right. but for coordination & normalization between items ( such as EPC items) cost factor ( with all of them, such as material, manpower , ... ) is better.

    M.Rashidi
  10. 0
    Mehdi Rashidi Alangeh ·
    Dear morteza,
    You are right. but for coordination & normalization between items ( such as EPC items) cost factor ( with all of them, such as material, manpower , ... ) is better.

    M.Rashidi
  11. 0
    Forum Guest ·
    Hello,
    I have a bad experience in this regards, I worked in EPC project in previouse project, , that project P was 90% based on cost, but actually most value of project was construction when work went to construction phase project had 82% our managers satirized us progress was very funnyfrom view of Time, P took 3 months but construction was done 12 months !! project director punished Planning group for this wrong actually that was not wrong it was correct based on cost !
  12. 0
    Morteza Jafari ·
    Hi Guest
    I accepted your experiance and I think you shall not insist to be Weight factor based on cost,
    what is your idea sombody else ?
  13. 0
    Mehdi Rashidi Alangeh ·
    Dear morteza,
    As you know cost factor is very stable for PM in the Oil & Gas Projects.
    In the fact any items convert to cost factor.

    your comment?
  14. 0
    Forum Guest ·
    Out of simplicity, I’ve been using the time based project percent complete that Suretrak calculates from activity percent complete data I provide weekly. In general, it seems to work quite well, except when there is a substantial delay, which can generate a reduction in percent complete.
    Has anybody noticed this? I’m I using the wrong parameter?
  15. 0
    Hal Macomber ·
    It depends on what you are looking to calculate. The usual percent complete measure addresses how much effort has been expended vs. how much effort was planned. One of my friends puts it this way, "THat’s why when you are 90% coplete, you still have another 90% to go!" She means that expending effort is not the same as producing results.

    The Microsoft MS Project development team noticed this a few years back when they were updating the s/w. The team leader decided to have the project team use ’Project 2000’ as the tool for developing ’Project 2002’. After only a few short weeks team members wanted off the project. They learned a number of lessons which you can read about at http://halmacomber.com/jammin/2002_08_25_archive.html#80714453. One of the more important lessons is monitoring completion. Tracking expended effort vs. planned effort they concluded was useless. They track percent of tasks completed as planned to be completed.

    In the construction world the approach is know as plan percent complete (PPC). The team tracks on a daily basis did they finish the work they planned to be finished on a daily basis. 99.5% complete is considered incomplete. You either got it done or not. You got no credit for completing work that was not planned for that time.

    This method brings attention to two key aspects of projects that Eli Goldratt speaks about in the Theory of Constraints: dependence and variability. The start of my work depends on the completion of your work. If I am to start without delay, then you must complete when you promise. The PPC measure places an emphasis on completing as promised rather than the effort to perform.

    Hal
    http://weblog.halmacomber.com
  16. 0
    Ernesto Puyana ·
    Your reflection is absolutely valid. That is why my percent complete figures regress from week to week, when not only activities planned have not been completed, but remanent durations extended time over time.

    Unless you finish what you planned, the measurement will make you look bad. That’s what is is for. isn’t it?

  17. 0
    Hal Macomber ·
    The PPC measurement is not designed to make you look bad when you don’t finish. It just works out that way! Actually, the people use the measure as a tracking metric. You want to see improving PPC on a week-to-week basis. If that is the case, then the team is managing their work. If PPC is flat or declining then there’s something the team needs to be learning. I’ve seen teams that approach achieving PPCs in the 90s as they get close to the end of their projects.
  18. 0
    Forum Guest ·
    hi,
    from reading all the replies, i think the discussion is genrally about the measurement of performance in EPC Contracts and to see if all tasks are being completed on schedule. the perimeter for the measurement of performance is percentage complete.
    i am working on the claim involing extension of time. as i have to mimic the actual schedules made by the subcontractor, the calendar variations and use of different softwares really creates a porblem e.g. CS Project schedules the activities for the same day as its predecessor finishes (I havent cleared out the concept Why it happens). so the durations of these tasks vary as calendars and start, finish dates vary.
    for the calculation of performance, i have two options:
    1-look for a time slice when a large number of activities was complete. or
    2-evaluate the percentage complete of a particular activity and use it.
    amazingly, the resluts appear quiet close to what the actual performance was. SO i would say that percentage complete does help.
    Safdar H. Hashmi
  19. 0
    Forum Guest ·
    With regards to EPC, normally the weight for P is the most higher, then, C and E is the least (based on the cost)
    For a particular project, i.e. in Oil & Gas industry, it started out with E, and about 30% or so the P will pick-up and then at about mid way the C begins. Therefore, I guess the weightage based on cost is the most appropriate, it starts low and pick-up as the P started and will never reached a point unles all the matls & eqpts being delivered. It will only finish off when the construction finishes.


Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?