Implementing PRINCE2 and a PSO
In the Open Standard
Graham FieldMember for 23 years 7 months
- Created
- 3
- 4
0
I am trying to set-up a project support office and rolling out Prince2 processes at the same time. Does anyone have any comments on the best way to proceed. I was proposing to only implement PIDs, High level Project plans, risks, Issues and Lessons learnt in the first roll-out followed by the QA/QR processes in a second phase.
Thanks
Graham
Thanks
Graham
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?