Activity-On-Arc(AOA), Activity-On-Node(AON).
In the Open Standard
Mustafa EgeMember for 21 years 5 months
- Created
- 14
- 8
0
In network planning techniques, such as PERT,CPM,
There are two possible ways of representing
each project: Activity-On-Arc(AOA), Activity-On-Node(AON).
we know that some project management computer packages use both the network representations.
is there real need for using the AoA representation (Because of minimum dummy arc problem)?
If the AoN representation is only used in project scheduling, what is the nature of the mistake made here?
I couldn’t find any clear-cut and admissible explanation.
Thanks to everybody for their contributions.
Mustafa Ege
There are two possible ways of representing
each project: Activity-On-Arc(AOA), Activity-On-Node(AON).
we know that some project management computer packages use both the network representations.
is there real need for using the AoA representation (Because of minimum dummy arc problem)?
If the AoN representation is only used in project scheduling, what is the nature of the mistake made here?
I couldn’t find any clear-cut and admissible explanation.
Thanks to everybody for their contributions.
Mustafa Ege
14 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?