Manpower/Cost Ratio between PMC and EPCC Contractor

Norzul IbrahimMember for 20 years 10 months
Created
3
2
0
Hi Guys,

PMC : Project Management Consultant
EPCC Contractor : Engineering, Procurement, Construction and Commissioning Contractor.

What is the optimum ratio of manpower/cost between the PMC and the EPCC Contractor?

Let say the total project cost(TPC) is USD 100 million. What will be the typical cost for the PMC? 5%, 10%, 15% of TPC?

Thanks

norzul

3 replies

Oldest first
  1. 0
    Norzul Ibrahim ·
    any advise?
  2. 0
    Devamalya De ·
    It will b anything b/w 1 - 2.5%. Less the project cost higher the % age and higher the project cost, lower the %age. For a project of USD 100 m, PMC fees is most likely to be in the 1.00 - 1.25% range upto a max of say 1.50%.
  3. 0
    Izam Zakaria ·
    Norzul, Is it u part of consultant???

Log in or join to reply