PEP and PQP

Mike GeorgeMember for 20 years 4 months
Created
5
2
0
Hi Friends,

I checked out project quality and execution plan but couldn’t find any clear difference. Could you please let me know their difference, actual deffinition and mailing sequence to client.

Best regards
George

5 replies

Oldest first
  1. 0
    Norzul Ibrahim ·
    Project Execution Plan vs Project Quality Plan?
  2. 0
    Norzul Ibrahim ·
    Based on our experience, PQP will be part of PEP
  3. 0
    Peter Holroyd ·
    to confuse
    PIP= PEP + Budget
    PEP is basically the method statement for the whole project in written format
    Below this document (which can get revised as the project enters new phases) sits a whole raft of more detailed document - one of which is PQP. This should detail the procedures and standards which will be used on the project - anything from design safety to goods received at site to billing the client. The best procedure is of course the one on Auditing of Project Quality and Quality Performance - or doesn’t anybody bother measuring Quality (or more important Quality Failure)any more in ther haste to GET THE JOB DONE ANYWAY?
  4. 0
    Zhang Haixiang ·
    PEP is a document that describe how to manage the project.
    It may cover construction management/method, quality control schedule(time control),contract/procurement control, EHS(saftey),document control.

    to support the PEP, there will be more detail documents/precedures for each part.
  5. 0
    Norzul Ibrahim ·
    Zhang,

    similar to my understanding...

Log in or join to reply