Planning for Roads& Infrastructure works
In the Open Standard
Mohsin FarooqiMember for 22 years
- Created
- 1
- 1
0
Hi my fellow Engineers im a Head Engineer (client) for a major B.O .T diamond industry (factories) total all 70 units. as iam new to Road works(B.T roads) there are certain problems iam facing regarding
1.A Single Sewerage treatment plant is enough for a plot 0f 200 acres in which there are 30 factories and the total number of employees are 50,000 till fully operational.The sludge is human waste.If we provide a single S.T.P the sewerage water will flow covering a distance of 6.5 km to S.T.P Initially there will be 5-10 factory units operational by 2008 whether it will reach the S.T.P or its better to provide seperate S.T.Ps for each units
2.The Sewerage lines are going within the roads and they are in median region i.e they run from the centre of road and not in service corridor i mean outside the roads.
its better to provide the sewerage lines within the roads or outside the roads which will be best ? or for any reasons we have to dug the roads in future patch work will be required ?. certain mainholes are 4mt depth whether maintenance of such mainholes is possible in future.
1.A Single Sewerage treatment plant is enough for a plot 0f 200 acres in which there are 30 factories and the total number of employees are 50,000 till fully operational.The sludge is human waste.If we provide a single S.T.P the sewerage water will flow covering a distance of 6.5 km to S.T.P Initially there will be 5-10 factory units operational by 2008 whether it will reach the S.T.P or its better to provide seperate S.T.Ps for each units
2.The Sewerage lines are going within the roads and they are in median region i.e they run from the centre of road and not in service corridor i mean outside the roads.
its better to provide the sewerage lines within the roads or outside the roads which will be best ? or for any reasons we have to dug the roads in future patch work will be required ?. certain mainholes are 4mt depth whether maintenance of such mainholes is possible in future.
1 reply
Oldest firstLog in or join to reply