Controlling of Re-Measurable Contract Project
In the Open Standard
Ponnaganti SridharMember for 22 years 2 months
- Created
- 5
- 3
0
i am here on small road project , which is a Re-Measurable contract.
Client here wants a Schedule in Excel did any one done a programme (Base-Line programme), as any one done a programmein Excel being a Professional.
is it possible to monitor a project of this kind with a S-Curve, maily the quitities keep on changing from the B.O.Q quantities every month because of Re-Measurable according to the work done on site.
and every week atleast Quantities cahnge and so, does the schedule as to keep on changing.
here i got typical type of Client
commments on this could me more help full for me
Sridhar