Controlling of Re-Measurable Contract Project

Ponnaganti SridharMember for 22 years 2 months
Created
5
3
0

i am here on small road project , which is a Re-Measurable contract.

Client here wants a Schedule in Excel did any one done a programme (Base-Line programme), as any one done a programmein Excel being a Professional.

is it possible to monitor a project of this kind with a S-Curve, maily the quitities keep on changing from the B.O.Q quantities every month because of Re-Measurable according to the work done on site.

and every week atleast Quantities cahnge and so, does the schedule as to keep on changing.

here i got typical type of Client

commments on this could me more help full for me

Sridhar

5 replies

Oldest first
  1. 0
    A D ·
    Hi Sridhar,

    Yaa, this type of scenario occurs if client staff doesn’t have any project management software as it is very costly to have multiple copies on such a smal project and most important, difficult to understand for the site team, as they are not used to large project environment.

    In one of the industrial Building project few years before, I have developed an S-Curve with a very small schedule in Excel. (If u provide too many details, its of no use, as client dont understand these type of schedules).

    S-Curve was fantastic and very easy to monitor.

    If u wanna hav a copy, mail me at ravirajab@yahoo.co.in

    Cheers,

    Raviraj
  2. 0
    Ife Olyke ·
    Hi Raviraj,

    I will also like a copy.

    olyke@yahoo.com

    Thanks.
  3. 0
    A D ·
    Just give me couple of days.
  4. 0
    Ponnaganti Sridhar ·
    Hi! Raviraj Bhedase,

    yes it is very easy to make Shedule in Excel, it is just like just makeing colour lines in Excel, as if we make like on a pice of paper, like drawing no logical links or no C.P.M nothing no meaning, i think for that you don’t need a professional planner,

    and coming to makeing the S-Curve it simply spreaing the cost according to the time of that activity and plot a curve but can you track the progress of the project like the one i am doing (Re-Measurable Contract)when there is no fixwd Budgeted Quantity in the project, the final Qualtities w’ll be according to the work exucuted on site

    any who iam very thankfull for your suggestions and may be very usefull if you send me the file which u have done to sridhar.p.kd@gmail.com
  5. 0
    Daniel Limson ·

    Since your project is a roadwork, Suggest you do a time chainage type of control which is based on length.

    Cheers,
    Daniel

Log in or join to reply