weekly manhour distribution

Nar ThapMember for 19 years 1 month
Created
4
4
0
I picked up the project from the middle which was a non resource loaded plan. Several weeks has passed now and I need to distribute the manhours on the activities. What is the most appropriate way to distribute the manhours so that weekly manpower histgram be generated? Nobody has info that the where the previous manpowers were consumed.
cheers

4 replies

Oldest first
  1. 0
    Bijaya Bajracharya ·
    If you are trying to generate mapower histogram for the past for which you don’t have records, I would ask why do you need that? It won’t be any productive exercise.

    The best thing is make a plan for the remaining manhours and start recording the actuals in a regular basis. That way after another several weeks, you (or someone in your position) won’t be in the same position as you are now.
  2. 0
    Larry Rino ·
    Nar, If you have the weekly quantities related to the consumed manhours, try to derive the weekly manhours from your actual production rates. I expect these manhours came from various quantities of completed work.

    I.e. Weekly manhours = Weekly production rates /
    Weekly quantities

    I hope these helps.
  3. 0
    Karthik Neostructo ·

    Dear sir,   Good morning

    Dear sir,

     

    Good morning everybody, i am new joining in planning planet, i am freshers also,

    i expert your guidence and help , i develop myself, pls coud u explain

     

    how to calculate the manhour for overall project, weekly, monthly,

     

    how to calulcate the production rate also

     

    i expert the valuable replay

     

    j.karthik

    nscl

  4. 0
    Mike Testro ·

    Hi Karthik Welcome to

    Hi Karthik

    Welcome to Planning Planet.

    Some advice - It is not a good idea to respond to a long dead thread - if you need help or advice then start a new topic in the appropiate section.

    Regarding your query the best source of cost and resource data is the project BoQ / Cost Plan - speak to the estimator / QS to get to what you want.

    If you are working with P6 and your WBS is set up correctly then it should be automatic.

    Best regards

    Mike Testro