REFINERY PROJECT

Jorge FierroMember for 22 years 11 months
Created
3
2
0
WHICH IS THE TYPICAL PACE (PROGRESS (%) PER MONTH) THAT CAN BE CONSIDERED FOR A REFINERY PROJECT, WITHIN THE NORMAL PARAMETERS (SINGLE SHIFT, THIRD WORLD COUNTRY, NO SEASONS, ETC.....).

THANKS!!!

3 replies

Oldest first
  1. 0
    Ian Thomson ·
    What sort of project? T/A involvement. No T/A Involvement
    Our major project worth 17 Million US dollars with no turnaround involved took 18 months.

    8 months to 10% design mainly, 11 months to 20%, then almost 10% a month to completion. Does that help?
  2. 0
    Jorge Fierro ·
    Ian Thanks.

    These figures gave me a good idea.

    Jorge
  3. 0
    Jay S ·
    It all goes about money.

    How fast can you spend it.

    To Spend 17 M in 18 Months is a slow project.

    I Have been on Project.

    1.8 B 36 Month (Engineering had to be done in 5 country’s / Fabrication in another & Construction in another

    100 M 7 Month All in One Country

    360 M 12 Months All In One Country

    25 M = 8 Months all in One Country.

    Some times it is not possible to spend money fast enough.


    So to answer it quickly if a Project Duration is 20 Month 3 to 7 % per Month

    If it is 10 Month 7 to 14 % per Months