Anybody knows where I can get help for Pertmaster??

Joel GilbertMember for 23 years 6 months
Created
1
34
0
Hi all,

I am importing a 7500 activities schedule with 15700 Links and multiple calendars, but it throws me a weird result when I open the project up after the import. Maybe there is something I need to do prior to importing? If anybody has experience in this please help me or a Pertmaster helpline site? Thanks

Joel

1 reply

Oldest first
  1. 0
    Joao Ribeiro ·
    Pertmaster is now owned by Primavera so you may be able to get some help at their site (entering Pertmaster support is still free). Also, you should check if you are using the latest version and sp (8.2 SP1) since there are known problems with importing schedules into Pertmaster.

    HTH
    Cheers.