can anybody tell tell me what the N value means in scheduling?
i have an idea about what it is but want to be sure


and

can somebody tell me the scope and step of building a schedule on a marginal field.

8 replies

Oldest first
  1. 0
    Anoon Iimos ·
    N? don’t know also,

    and "marginal field"? if you can explain a little more, maybe I have some idea
  2. 0
    Anoon Iimos ·
    for marginal field, I believe It’s quite difficult, I had just seen (on tv) a small town in Alaska (around 150 people living) and the only means for transportation is chopper, not to mention that the place was never been reach by their governor who happens to be running as... and one odd thing is some people thought they are part of Russia which is a few miles away.
  3. 0
    Se de Leon ·
    I encounter N-value when I want to interpret a geotechnical report. This blow count will indicate how hard or how soft the bearing surface for foundation.

    If you’re asking specifically in scheduling norms like in Critical Path Analysis, I haven’t encountered this if there is any.
  4. 0
    Daniel Limson ·
    You might have mis-heard it, maybe they were referring to "earned value"
  5. 0
    Neeraj Agarkar ·
    Only time I have come across N value is SPT values during soil investigation. The blow count is used to determine soil bearing capacity.
    Are you by any chance working in exploration projects?
  6. 0
    Se de Leon ·
    Hi Daniel,

    You could be right. He might have misheard earned value as N value. That’s funny.

    Hi Neeraj,

    Yeah you’re right. N-value can be found from an SPT/Bore Log report. I don’t work for a geotechnical company but for a design build company.
  7. 0
    Samer Zawaydeh ·
    Dear oladapo,

    Going to your original question, the steps to building a schedule are best summarized in the PMI "Planning Process Group". I will list the processes that enables you to create a schedule as follows:

    1. Develop Project Management Plan.
    2. Scope Planning.
    3. Scope Definition.
    4. Create Work Breakdown Structure.
    5. Activity definition.
    6. Activity sequencing.
    7. Activity resource estimating
    8. Activity Duration estimating
    9. Schedule Development.

    If you have any other question, please let me know.

    Good Luck,

    Samer


  8. 0
    Anoon Iimos ·
    i believe oladapo is referring to Math or something