incomes Vs cost for the BoQ items
In the Open Standard
Mario SabbioniMember for 18 years 1 month
- Created
- 3
- 1
0
I’ve loaded in P6 300 items of the BoQ with the prices the company is charging. Now I can print the S curve with the foreseen incomes.
My chief has asked me to load the cost the company pays for each item of the BoQ.
Considering that I have to use different codes (e.g. item 0001(+)Vs item 0001 (-)), how can I see the S curve of the only (+)/(-) items?
PLS send me a hint if you know how to work it out
Thanks
My chief has asked me to load the cost the company pays for each item of the BoQ.
Considering that I have to use different codes (e.g. item 0001(+)Vs item 0001 (-)), how can I see the S curve of the only (+)/(-) items?
PLS send me a hint if you know how to work it out
Thanks
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?