Clause 56 Actual & Correct Quantites

Vijay DurairajMember for 17 years 4 months
Created
5
2
0
Can you please explan me the influnce of omition on this type of contract.how can we do the valuation?

5 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Vijay,

    It depends on the stage at which the omition notice was issued.

    If the Engineer asked to omit a certain item at the beginning of the Contract, then the Contractor can ask for the amount of overhead and profit that was added to this cost of deliverable.

    On the other hand, if the omition notice was issued at a later stage after the approval of the Material and Shop drawings, then the Contractor can ask for the cost of the material as well, withou the cost of installation or construction.

    It depends on the item and the Conditions of Contract as well. If you give us more information, we can answer you in more details.

    With kind regards,

    Samer
  2. 0
    Mike Testro ·
    Hi Vijay

    Samer’s advice is sound - but there are other considerations.

    The employer cannnot deduct work from your contract to give it to another contractor unless you agree terms in advance.

    As well as cost considerations most contracts will not allow a reduction in time for ommission of work.

    The only time such matters can be taken into consideration is if the contractor is claiming an EoT for other events.

    Best regards

    Mike Testro.
  3. 0
    Vijay Durairaj ·
    hai Mike Testo /Samer
    Thanks

    Mr Mike
    for the final account ,say for Eg ;as per as built some works are not executed by contractor due to drawing revisions .In this case what will happen to the original bill items which are not executed.

    for the final account will they omit?

    Please advise me
    Regards
    Vijay
  4. 0
    Andrew Flowerdew ·
    Vijay,

    As you refer to Cl56, I assume it’s a form of FIDIC contract.

    One other important general consideration as to how omissions are dealt with is whether the contract is lump sum or remeasurable. i.e, which party took on the risk of the quantities?

    Generally, the party who took the risk gets the benefit - or pays the price if things go the other way.
  5. 0
    Samer Zawaydeh ·
    Dear Vijay,

    If you describe the problem in more details you will get a better answer.

    With kind regards,

    Samer