Ladder relationship and critical path
In the Open Standard
BK
Balu KarunakaranMember for 18 years 10 months
- Created
- 13
- 5
0
13 replies
Oldest first- 0MTMike Testro ·Hi Balu
Why do you want to fiddle your programme to make an articial critical path?
There are many threads on ladder programmes for you to search your answer.
Basically ladders are good for production line factory programmes with lots of repetion - they are of little use in construction.
Best regards
Mike Testro - 0SZSamer Zawaydeh ·Dear Balu,
You can do that by making their float = 0. Any way you can think of achiving that.
The activity will become critical if you do not work on it at the right time and when its float is zero. You might want to try to change the starting date to an earlier date. This will make it become critical faster.
With kind regards,
Samer - 0SPSergey Prazdnikov ·I agree not to use constrains at all. Otherwise it’ll break schedule logic.
I suggest you should change the criteria of critical path.
Put total float <= 5 days or 10 days (instead of default total float <=0) In that case all near critiacl activities come to the critiacal path and become "red" on the gantt chart. It is also give you some additional time (Float) to control activities before they become really critical. - 0SDStephen Devaux ·In terms of not using calendar-based constraints, I agree with Mike 99.9%. The one exception is if a constraining factor is TRULY calendar driven (e.g., for some reason, you HAVE to wait for the full moon, or for a comet to reach a certain point), and you know EXACTLY when that will occur.
But if you DO use constraints, two rules to follow:
(1) Input each constraint separately, one at a time, and see what the impact is. If you can’t live with the impact of a specific constraint, you’re going to have to figure out a way around it.
(2) FILTER OUT all constraints (and LOEs!) when doing what-ifs and other schedule analysis. The constraints will constrain (!?) your (and the software’s) ability to push things around and see the impact.
For example, constraints and LOEs will erroneously change the drag calculations in MSP (and I suspect in Spider Project -- Vladimir?).
Finally, as has been said, the issue of playing around with float is a dangerous game. And, as for highlighting all activities with less than a certain amount of float, sure, do that if it reminds you to keep track of paths with limited float.
But ultimately, what’s important to project completion is drag -- if the second longest path has 5D of float, that means the CP tasks at that part of the schedule can have up to 5D of drag. That’s crucial info -- use it NOT to justify "pacing" the project and letting the second longest path slip by 5D, but to pull in the longest path by 5D or more. And then iterate the process on whatever activities are now on the longest path.
This optimization process is crucial -- if my project MUST be completed by June 30, I’d much rather have a schedule where the longest path is scheduled for completion June 10 and there are 12 other paths with less than 5D float than a schedule where the longest path is scheduled for completion June 29, and the next 12 longest paths all have 15D - 20D float. And that’s how you generate your schedule reserve.
Fraternally in project management,
Steve the Bajan - 0TATanveer Ahmad Niazi ·
hi, I am new in the forum and
hi, I am new in the forum and in planning as well, can any one tell me about "Claim Digger" in the forum or by tanveeraniazi@yahoo.com, Thanx